Progress of Work at Small Hydroelectric Power Plant Construction Sites

An active phase of construction and installation work continues at the small hydroelectric power plant (SHPP) facilities in accordance with the approved production schedule. SHPP-1 Block: Brick walling works have been completed. The construction crew has commenced roofing work, as well as the installation of window and door units for the building. At the 2nd-stage […]

Progress of Work at Small Hydroelectric Power Plant Construction Sites Read More »

Construction Progress of the Small HPP Cascade: Works at the SHPP-1 Site

The company continues the implementation of the project for the construction of a small hydropower plant cascade on the Turgen River. Currently, works at the SHPP-1 site are progressing at an active pace. Key Stages of Work: All processes strictly comply with the approved construction schedule and technical regulations.

Construction Progress of the Small HPP Cascade: Works at the SHPP-1 Site Read More »

Active construction and installation works continue at HPP-1

The installation of column formwork has been completed for the HPP-1 building. Preparation for concrete works is currently underway. In parallel, preparation of the excavation pit for the pressure basin is ongoing. The assembly of steel anchor supports has also been completed, and their installation has already begun. Works are proceeding according to schedule at

Active construction and installation works continue at HPP-1 Read More »

Installation of Intermediate Transmission Line Poles Completed at Turgen HPP, Earthworks Ongoing

Construction works continue at the Turgen HPP site in the Ak-Suu district. As of April 26, the installation of intermediate reinforced concrete transmission line poles (type SK22) has been completed. At the same time, earthworks are underway for the derivation bench of the first small hydropower plant (1 SHPP). Construction at the site is proceeding

Installation of Intermediate Transmission Line Poles Completed at Turgen HPP, Earthworks Ongoing Read More »

27 Transmission Line Towers Installed at Turgen HPP, Substation Construction Underway

Construction work continues at the Turgen HPP site in the Ak-Suu district. As of early April, 27 intermediate transmission line towers have been installed. At the same time, construction of the 35/10 kV “Novo-Voznesenovka” substation is underway. Currently, foundation preparation for the substation portal is in progress. Work at the site is ongoing as planned.

27 Transmission Line Towers Installed at Turgen HPP, Substation Construction Underway Read More »

Construction work has begun to connect the SHP to the NESK network at the “Novo-Voznesenovka” substation

Since February of this year, construction work has begun on the project to connect the Small Hydropower Plant (SHP) to the networks of JSC “National Electric Grid of Kyrgyzstan” at the 35/10 kV “Novo-Voznesenovka” substation (35 kV Zhyrgalan overhead line) with the construction of a 35 kV overhead line in the Ak-Bulun rural community, Ak-Suu

Construction work has begun to connect the SHP to the NESK network at the “Novo-Voznesenovka” substation Read More »

LLC “Chon-Ak-Suu Hydro-Energy” signed a contract with the Turkish company SUPERLIT for the supply of pipes

On March 9, 2026, LLC “Chon-Ak-Suu Hydro-Energy” signed a contract with the Turkish company SUPERLIT for the supply of GRP fiberglass pipes and fittings for the diversion channel of the small hydropower plant (SHP). SUPERLIT is a leading international manufacturer and supplier of fiberglass piping systems since 1961, serving various projects in hydropower, irrigation, and

LLC “Chon-Ak-Suu Hydro-Energy” signed a contract with the Turkish company SUPERLIT for the supply of pipes Read More »

Construction on the cascade of small hydropower plants in Turgen has doubled in pace

Large-scale works are underway at the cascade of small hydropower plants in the Turgen Gorge with doubled intensity. At present, the backfilling of the wall of the second settling tank block has been fully completed, ensuring increased structural stability. On the first settling tank block, flat gates—key elements for regulating water flows—have been successfully installed.

Construction on the cascade of small hydropower plants in Turgen has doubled in pace Read More »