An active phase of construction and installation work continues at the small hydroelectric power plant (SHPP) facilities in accordance with the approved production schedule.


SHPP-1 Block: Brick walling works have been completed. The construction crew has commenced roofing work, as well as the installation of window and door units for the building. At the 2nd-stage forebay site, the placement of the rebar cage has been completed, and wall structure concreting is underway.

SHPP-2 Site: The construction of the monolithic reinforced concrete frame below the “zero” mark has been fully completed. Specialists have proceeded with the rebar placement and concreting of load-bearing columns and floor slabs below the zero-cycle level of the SHPP building.

SHPP-3 Site: Earthworks for the excavation and preparation of the foundation pit are in progress. Work has commenced on the sand-and-gravel bedding and the concreting of the SHPP building foundation slab.
Electrical System and Substation Facilities:

SHPP-1 Substation: Installation and mounting of the main power transformer have been successfully completed in cooperation with the commissioning engineer from TBEA (China).

SHPP-2 Substation: Perimeter fencing construction is complete. Electrical engineers have started installing and mounting the main power equipment of the substation.

SHPP-3 Substation: Installation of the power transformer into its design position has been completed. Work is ongoing to construct the grounding loop and install busbars.

Diversion Canal Works: Preparation of the trench is underway, bringing the base to the design levels. Works include layer-by-layer compaction of ground sections, as well as backfilling and compaction of the crushed stone pillow for structural laying.