The company continues the implementation of the project for the construction of a small hydropower plant cascade on the Turgen River. Currently, works at the SHPP-1 site are progressing at an active pace.
Key Stages of Work:
- Hydraulic Structures: construction and assembly works are being carried out on the main building of SHPP-1, and the excavation of the diversion canal trench is underway.
- Power Infrastructure: in parallel, the installation of technological equipment for the SHPP-1 substation is being performed.
- Power Transmission Lines: the installation of PB35-4 anchor towers has been completed in accordance with the project coordinates; the assembly of subsequent towers of this type is ongoing.
All processes strictly comply with the approved construction schedule and technical regulations.