Active construction and installation works continue at HPP-1

The installation of column formwork has been completed for the HPP-1 building. Preparation for concrete works is currently underway.

In parallel, preparation of the excavation pit for the pressure basin is ongoing. The assembly of steel anchor supports has also been completed, and their installation has already begun.

Works are proceeding according to schedule at all designated sites.