Construction progress has been achieved at several facilities of the small HPP cascade in the Turgun Gorge. Contractors have completed earthworks and monolithic work.
Completed work:
- HPP-1 Building: Backfilling of the pit has been completed. This step finalizes the zero-cycle work and prepares the site for further construction.
- Settler Structure: The installation of wall formwork has been fully completed. Work has now begun on pouring concrete into the prepared structures at the same facility.
- Settling Basin: Gates have been installed. The installation of this equipment is an important step before commissioning.
The construction of the small HPP cascade is proceeding according to the approved schedule.